What happened
Houston-based geothermal startup Quaise Energy said on Tuesday that Google will purchase 50 megawatts of carbon-free electricity from Project Obsidian, the company's first commercial plant, planned near the Newberry Volcano in central Oregon, Canary Media reported. Google intends to use the power for its existing data center operations in northwest Oregon, possibly starting in 2030.
Quaise confirmed the agreement is worth more than $500 million. The startup expects the Oregon plant to cost roughly $350 million to build and is seeking buyers for a further 200 MW of planned capacity at the site. Chief executive and president Carlos Araque described the deal as an important step for both Quaise and the wider clean energy sector.
Quaise plans to begin with oil-and-gas drilling tools to build an enhanced geothermal system. At a depth of about 2.5 miles, it intends to switch to millimeter-wave drilling, which uses high-frequency beams to melt and vaporize rock. The goal is to reach rock hotter than 572 degrees Fahrenheit and draw more energy from fewer wells. The technology is still being tested at a field site in central Texas.
Context
Quaise raised $180 million in equity in August, including from drilling firm Nabors Industries. At least four US geothermal firms now have tech-giant deals: Fervo Energy will supply Google with nearly 400 MW from Cape Station in Utah, and Sage Geosystems and XGS Energy are partnering with Meta in Nevada and New Mexico. Mazama Energy recently raised $135 million for a superhot project near Newberry.
简报
一封邮件,尽览一周科技要闻。
每周精选值得一读的报道。可随时退订。