Think tank pitches heat batteries as a faster clean power option for off-grid data centers

An Energy Innovation report puts solar- and wind-charged thermal storage at about $120 per MWh, while startup Cache Energy says it can scale output quickly.

INSIGHTEX Editorial Desk

2 min read

Think tank pitches heat batteries as a faster clean power option for off-grid data centersIntelligence Report

What happened

A report from think tank Energy Innovation argues that off-grid data centers could get round-the-clock power from large thermal batteries charged with inexpensive solar and wind electricity, Canary Media reported. Author Eric Gimon, a senior fellow at the group, said the approach can compete on cost with fossil gas in many U.S. regions and could be running within one to two years where renewables are being developed.

Gimon estimated that these hybrid systems, which heat materials above 1,000 degrees Celsius and later use that heat to drive steam turbines, could supply firm power for roughly $120 per megawatt-hour, including the renewables. He said only about 40% of stored energy is recovered, far below lithium-ion batteries, but that the technology still comes out cheaper than lithium-ion over longer storage durations. He added that he knows of no U.S. data center using the setup yet.

Arpit Dwivedi, founder and CEO of thermal storage startup Cache Energy, said his company can already produce about one gigawatt-hour of systems a year. He estimated it could reach 10 GWh annually within 12 months and 100 GWh within 24 months. Dwivedi said Cache Energy has held talks with data center developers, and that wider adoption will depend on one or two working projects in that setting.

Context

Data center developers have turned to building their own gas plants to secure electricity, facing high equipment costs, long turbine backlogs, pipeline limits and local opposition. Estimated costs for dedicated gas power range from about $72 per MWh in West Texas to the $140 to $165 per MWh that Jeffries estimated Meta pays for an off-grid plant in Ohio. Utilities and states are also pressing data centers to supply their own, cleaner power.

SourceCanary Media